Construction of Vinh Hao 220kV substation and connection lines

On 6 March 2022, in Binh Thuan, Power Project Management Board 2 (PPMB2) coordinated with contractors to organize the construction of Vinh Hao 220kV substation and connection lines. The project is expected to be completed and energized in the third quarter of 2022.

Delegates performed the groundbreaking ceremony to implement the project

Vinh Hao 220kV substation is invested and built in the unmanned model with two 220/110kV-250MVA transformers and newly built about 1.3km of connecting 220kV line.

The project has a total investment of more than VND 211 billion. The project is located in Vinh Hao commune, Tuy Phong district, Binh Thuan province, invested by Vietnam Electricity, and managed and operated by PPMB2.

The construction unit is a joint venture of contractors named Telematic Joint Stock Company - 3C Control Communications Computer Joint Stock Company - Power Construction Consulting Joint Stock Company 4 - TOSHIBA Vietnam Transmission and Distribution System Co., Ltd. Nam - Alphanam E&C Joint Stock Company.

The project was invested and built with the goal of strengthening the transmission grid capacity, releasing the capacity of renewable energy sources in Binh Thuan province and neighboring provinces, ensuring reliable operation of the  Phan Ri - Ninh Phuoc 110kV transmission line.