EVN accepts and puts into use Phuoc Thai 1 Solar Power Plant

On 7 August, 2020, in Ninh Thuan province, Mr. Nguyen Tai Anh - Deputy General Director of Vietnam Electricity (EVN), Chairman of EVN’s Investor-level Acceptance Council and members of the Council conducted  aAcceptance and agreed on putting acceptance of the Phuoc Thai 1 Solar Power Plant into use.

Phuoc Thai 1 Solar Power Plant, with a capacity of 50MWp, uses polycrystalline photovoltaic panel technology. It includes a central inverter and Phuoc Thai 220kV substation, with a capacity of 2x125MVA. In its initial investment phase, Phuoc Thai 1 Solar Power Plant was installed with one transformer 125MVA and associated equipment systems; construction of a double-circuit 220kV power line of 2.3km long. For the time being, connection had been made to one circuit of Vinh Tan-Thap Cham 220kV double-circuit power line.

In addition, many other items of construction had been performed, for example items serving construction works, associated items, remote control and supervision systems, measuring and observation stations, etc.

The assessment of the Acceptance Council affirmed that the scope of performance met the approved design. The quality of the project, the construction and installation of the work items met the design requirements, the technical specifications and the installation instructions of the equipment supplier.

The Acceptance Council checking and inspecting solar panels at the Phuoc Thai 1 Solar Power Plant project

All equipment had been tested and calibrated in accordance with current technical standards and regulations.

Ninh Thuan Province Police Department of Fire Prevention and Fighting and Rescue issued Certificate No. 1002/PC07 dated 16 July 2020 for acceptance of fire prevention and fighting system of Phuoc Thai 1 Solar Power Plant.

EVN's Deputy General Director Nguyen Tai Anh, Chairman of the Acceptance Council chairing the meeting

“The Council agreed to accept the project to be put into use. The Investor-level Acceptance Council assigned Vinh Tan 4 Thermal Power Plant to receive, manage and operate Phuoc Thai 1 Solar Power Plant and coordinate with Power Project Management Board 3 to supervise the implementation of contractor's guarantee obligations,” concluded EVN's Deputy General Director Nguyen Tai Anh.

Phuoc Thai 1 solar power plant project:

- Construction site: Phuoc Thai commune, Ninh Phuoc district, Ninh Thuan province;

- Total investment: VND1,113 billion;

- Investor: Vietnam Electricity;

- Representative of Investor: Power Project Management Board 3;

- Commencement: 26 September, 2019;

- Commercial electricity generation: 9 July, 2020 (planned for 31 July, 2020);

- By the end of 7 August, 2020: Generated 7.2 million kWh of energy.


  • 08/08/2020 03:16
  • evn.com.vn
  • 260