The project has total investment of VND 364 billion, invested National Power Transmission Corporation (EVNNPT), managed by CPMB on behalf of EVNNPT, operated by Power Transmission Company No. 3 (PTC3).
The substation consists of two transformers of 220/110kV – 125MVA; distribution system of 220kV including 8 feeders, in this stage, equipment is installed for 6 feeders; distribution system of 110 kV including 14 feeders, in this stage, equipment is installed for 8 feeders.
Energizing 220-kV Substation of Dak Nong will contribute to improving power supply capacity, which satisfies highly increasing load demand in Dak Nong province; enhance safety, reliability, stability in operation and quality of power for the regional power system, at the same time, limit power losses in the transmission grid.