Transformer 1 at Lieu De 110kV substation
Construction of Lieu De 110kV substation started on 30 June 2020 by Northern Power Corporation as the investor, with a total investment of VND136.8 billion. The substation is built with the unmanned model, creating a premise for smart rural power network development.
The project has an installation scale of two transformers (2x40MVA), with one transformer installed in the first stage; installation of control, protection, measurement, communication, SCADA, surveillance cameras and automatic fire prevention and fighting systems.
Lieu De 110kV substation will contribute to improving the reliability of power supply, reducing power loss, ensuring safe and stable power supply in Nghia Hung, Truc Ninh and Nam Truc districts.
The project contributes to improving power quality, strengthening grid connection, reducing voltage loss in the medium voltage network, meeting the load demand for the southern districts of Nam Dinh province during the hot summer season in 2021.