The project started in September 2021. According to the committed schedule with the investor of Van Phong 1 BOT Thermal Power Plant, this project must be completed before 26 December 2022. The construction time of this project is very short compared to other projects of similar size and nature.
Leaders of EVNNPT and its units participating in the project witnessing the moment of energizing Van Phong 500kV substation and connections on the morning of 28 November 2022
EVNNPT/CPMB prepared their detailed schedule of each work item, closely followed the construction site to urge supervision, promptly solved problems, speeded up the progress, and ensured the project's quality. The Management Board and the Front Board are responsible for managing construction details, standing on site to promptly coordinate with units and localities to solve problems arising during the construction process.
The Van Phong 500kV substation and its connections are energized and ready for trial operation of the Van Phong 1 BOT Thermal Power Plant
The energizing of a project ensures a safe and continuous power supply for the load in Khanh Hoa province and neighboring provinces; meets the socio-economic development needs of the key economic region of the South Central Coast; releases the capacity of Van Phong 1 BOT power plant and capacity of renewable energy power plants in Ninh Thuan, Khanh Hoa, and Phu Yen provinces; contributing to ensuring the N-1 criterion, strengthening the stability of the power system, improving the reliability and safety of power supply for the national power system.
Van Phong 500kV substation
Continue to work hard to complete the entire cluster of works
Leaders of EVNNPT and its units participating in the project at the countdown timer installed at the Van Phong 500kV substation
EVNNPT Deputy General Director Truong Huu Thanh said: The energizing of the Van Phong 500kV substation project and its connections timely serves the testing power generation of Van Phong 1 BOT thermal power plant and is ready to release the plant's capacity. However, to release the plant's full capacity, it is necessary to complete the Van Phong - Vinh Tan 500kV power line. Currently, EVNNPT and its units participating in the project are striving to complete the project in December 2022 under the direction of the Government and Vietnam Electricity.
Van Phong 500kV substation and connection lines:
- Vietnam Electricity assigns EVNNPT to be the investor;
- The Central Power Project Management Board on behalf of the investor manages the project;
- Construction site: Ninh Hoa town, Khanh Hoa province;
- Total investment: About VND 1,098 billion;
- Design consultancy unit: Power Engineering Consulting Joint Stock Company 2;
- Supervision Consultant: Joint Venture of Power Engineering Consulting Joint Stock Company 4 and International EVN Joint Stock Company;
- Construction and installation units: Alphanam E&C Joint Stock Company and Hai Phong Power Construction and Investment Joint Stock Company;
- Unit of transformer installation and calibration experiment: Power transmission engineering service company;
- Operational management unit: Power Transmission Company No.3
|