Energizing first GIS 220kV substation  in Da Nang city

On the evening of September 30, 2024, the Central Power Project Management Board (CPMB) coordinated with relevant units to successfully energize the Hai Chau 220kV Substation and the Hoa Khanh - Hai Chau 220kV Transmission Line. This is the first GIS substation in Da Nang city.

The Hai Chau 220kV Substation Project and the  Hoa Khanh - Hai Chau 220kV Line are invested by the National Power Transmission Corporation (EVNNPT), managed by CPMB, and operated by Power Transmission Company No. 2.

The project is designed with a scale of building a new 220/110/22kV GIS-type substation, with a capacity of 2x250MVA. In this phase, a 250MVA transformer shall be installed; investing in the construction of 2 circuits of the Hoa Khanh - Hai Chau 220kV line, nearly 10km long, of which the length of the underground cable section is more than 7.3km (this is also the first underground cable line in Da Nang City), the length of the overhead line is nearly 2.6km. The project also builds a 22kV underground cable line with a length of 121m to supply self-consumption power to the  Hai Chau 220kV substation.

CPMB representatives and related units witnessing energizing moment of Hai Chau 220kV substation - Photo: Le Linh

The project helps to increase the power supply capacity, meeting the load development needs of Da Nang city and the region.


  • 01/10/2024 04:02
  • Translator: Mạnh Hùng
  • 128