Energizing wiring circuit 2 of Thanh Hoa–Nghi Son–Quynh Luu 220kV transmission line project

The Northern Power Projects Management Board (NPMB) has completed the wiring circuit 2 of  Thanh Hoa-Nghi Son-Quynh Luu 220kV transmission line project on Thanh Hoa-Vinh 220kV transmission line and energized at 1:03 on 28 April 2022.

The project has a scale of pulling ACSR 330/43 conductor with a length of 82km, including 67 anchorages from Ba Che 220kV substation to Nong Cong 220kV substation, Nghi Son 220kV substation and Quynh Luu 220kV substation; construction and installation of a new 220kV bay at Ba Che 220kV substation, along with some other items.

  

NPMB has completed the wiring circuit 2 of Thanh Hoa-Nghi Son-Quynh Luu 220kV transmission lines

The project is invested by the National Power Transmission Corporation and plays an important role in capacity releasing for Nghi Son 2 BOT Thermal Power Plant through the 220kV power grid, increasing the reliability of the power system, especially contributing to ensuring stable power supply for the load in Thanh Hoa, Nghe An and northern provinces before the hot season in 2022.

The project was completed and energized to celebrate the Liberation of the South and national unification on April 30 and the International Labor Day on May 1.