Information about failures of some substations in the North on 4 July 2022

According to information from the National Load Dispatch Center, at 13:00 on 4 July 2022, voltage fluctuations appeared on the Northern power system, affecting some customers' power supply in the North.

The initial cause was determined hot weather, which increased power consumption and some generator units failed causing voltage fluctuations, then power supply interruption resulted in some customers in the North.

Immediately after the failure occurred, the National Load Dispatch Center actively coordinated with power generation and grid operating units to troubleshoot the problem and restore power supply to customers as quickly as possible.

By 15:00 on the same day, all customers who were affected by power disruption had been restored to the power supply and the Northern power system have returned to stable operation.

Vietnam Electricity is looking forward to receiving sympathy and sharing from power customers about the power supply interruption mentioned above.

CONTACT INFO:

Communication Department - Vietnam Electricity

Email: bantt@evn.com.vn

Phone: 024.66946405/66946413; 

Fax: 024.66946402        

Address: No. 11, Cua Bac Street, Truc Bach Ward, Ba Dinh District - Hanoi;

Website: www.evn.com.vnwww.tietkiemnangluong.vn

Fanpage: www.facebook.com/evndienlucvietnam

Information%20about%20failures%20of%20some%20substations%20in%20the%20North%20on%204%20July%202022.docx


  • 04/07/2022 10:48
  • evn.com.vn
  • 1385