At the meeting, Mr. Hirohide Sagara said that, despite being affected by COVID-19 pandemic, Nghi Son 2 BOT thermal power plant project has reached 80% of the plan, surpassing the plan.
In order for the project to achieve this result, there is a great contribution and support of Vietnam Electricity; at the same time, thanks given to EVN for standing side by side with the investor during the past time in solving the project's difficulties and obstacles.
Mr. Hirohide Sagara - General Director of Nghi Son 2 Co., Ltd., (on the left) highly appreciating EVN's support in recent years.
Mr. Tran Dinh Nhan - General Director of EVN said that according to the forecast, the situation of power supply in 2021 as well as the following years will face many difficulties. Therefore, the operation of Nghi Son 2 BOT thermal power plant will make significant contribution in electricity supply.
Recently, EVN has been actively working with the Government, the Ministry of Agriculture and Rural Development to convert the forest land of the 500kV transmission line connecting BOT Nghi Son 2 power plant and achieve positive results.
In parallel, the Group has been working closely with investors, leaders of Thanh Hoa and Nghe An provinces to solve difficulties and problems in site clearance of 500kV transmission line connecting Nghi Son 2 BOT power plant.
In the coming time, the Group will continue to direct the National Power Transmission Corporation, the Management Board of Central Power Projects to maximally concentrate forces, accelerate the construction progress of the 500kV transmission line project, with the target of completing the project in October 2020, promptly releasing capacity of Nghi Son 2 BOT power plant.
EVN leaders suggested the investor of Nghi Son 2 BOT power plant investor continue to work closely with EVN and Thanh Hoa and Nghe An provinces to handle shortcomings in ground clearance and accelerate the construction of 500kV line.