Project of Quang Trach - Pho Noi 500kV line, circuit 3: Localities need to hand over entire site before March 30

That is the request of comrade Nguyen Hong Dien - Standing Deputy Head of the State Steering Committee for important national programs, works, and projects, key energy sectors (Steering Committee), Minister of Industry and Trade (MOIT) at the meeting on the Quang Trach - Pho Noi 500kV line, circuit 3, on March 12.

Attendants at the meeting in Hanoi were representatives of ministries and branches who are members of the Steering Committee (Committee for Management of State Capital at Enterprises; Ministry of Agriculture and Rural Development; Ministry of Transport).

The meeting was connected to the online station of the People's Committee of 9 provinces with the project of Quang Trach - Pho Noi 500kV line, circuit 3: Quang Binh, Ha Tinh, Nghe An, Thanh Hoa, Ninh Binh, Nam Dinh, Thai Binh, Hai Duong, Hung Yen.

For EVN's side, the attendants were EVN’s President and CEO Nguyen Anh Tuan, EVN’s Vice President Pham Hong Phuong, and General Director of the National Power Transmission Corporation (EVNNPT) Pham Le Phu.

Provinces continue to coordinate with EVN and EVNNPT in project implementation

Although the handover of the site of foundation pits achieved 100% as required, in reality, the construction contractor did not have easy access to these locations, and there are still difficulties that require the participation of local authorities. To date, only 31.8% of the project's site of anchoring space has been handed over. Most localities committed to completing the handover on March 30, but there are still localities that proposed handing over the premises in early April. Thus, compared to the progress required to complete the project in June, this is still a challenge for the investor.

Standing Deputy Head of the Steering Committee, MOIT Nguyen Hong Dien making speech

Comrade Nguyen Hong Dien also emphasized that the Government issued Decree No. 27/2024/ND-CP dated March 6, 2024 amending and supplementing a number of articles of Decree No. 156/2018/ND-CP dated November 16, 2018 of the Government, detailing the implementation of a number of articles of the Forestry Law; which regulates temporary use to carry out the construction of temporary works to serve the construction of power grid projects for socio-economic development for national and public benefits in accordance with the provisions of law on construction, electricity and other relevant laws. It is recommended that the Ministry of Agriculture and Development continue to closely monitor and guide EVN and EVNNPT in implementation; and instruct in handling problems that arise during implementation.

MOIT directed EVN and EVNPT to urgently perform construction of all foundation positions in March, ensuring enough conditions to complete the project in June.

Perform construction simultaneously, throughout the entire route

At the meeting, President and CEO Nguyen Anh Tuan reported to the Steering Committee on the implementation status of the project of the 500kV line, circuit 3, from Quang Trach to Pho Noi. To date, a total of 4 component projects have handed over 1,177/1,177 post-foundation positions (100%) and 160/503 anchoring spaces (reaching 31.8%), while 343/503 anchoring spaces have not yet handed over the site.

EVN’s President and CEO Nguyen Anh Tuan reporting on project implementation status

Construction work is currently being deployed simultaneously across the entire route at 1,174/1,177 locations (about 99.7%).

EVNNPT’s General Director Pham Le Phu commits to completing the project on schedule

EVN has requested the People's Committees of the provinces to direct and urge departments, branches, and localities to continue paying attention to handling arising problems; and complete the handover of the route corridor no later than March 30, 2024. EVN also proposed that, regarding the resettlement work, the provinces should direct the People's Committees of the districts/Councils of site clearance of the districts to urgently inventory, count, and determine the number of houses/households that shall be relocated and resettled before March 15, 2024.


  • 12/03/2024 10:33
  • evn.com.vn
  • 56