Unit 2 of Lai Chau Hydropower Plant Synchronized to National Power Grid

After four days of off-load operation, at 09:15 on 20 June 2016, Unit No. 2 of the Lai Chau hydropower plant with capacity of 400 MW was successfully synchronized to the national power grid.

The Lai Chau hydro-power project has a total investment of VND 35,700 billion. It is the hydropower plant project of special level constructed on the Da river.  

The main task of the project is to supply power to the national power system, contributing to the flood control in the rainy season, water supply in  the dry season for the Northern Plains,  promoting socio-economic development of the provinces of  Lai Chau, Dien Bien and the North-Western region, ensuring the national security and defense of the Northwestern region.

Unit No. 2 of Lai Chau hydropower plant successfully synchronized to the national grid- Photo: Minh Ngoc. 

Unit No 2 of the Lai Chau hydropower plant generated power on schedule as required by the Vietnam Electricity. This is also one  of important prerequisite factors to ensure the progress of completion and generation of power of Unit No.3 expected in November 2016. The whole project shall be completed in 2016, one year ahead of the approved schedule.

Mr. Pham Hong Phuong-Director of the Son La – Lai Chau hydropower project management board   said: In the coming time, the labour forces from the contractors, the consultants and the project management board, etc., will further enhance the inspection, supervision, progress monitoring, quality of installation, equipment supply; finalizing remaining items of the scenery, etc., to ensure the inauguration progress of Lai Chau hydropower plant project in December 2016.

Reportedly, as of this moment, Lai Chau hydropower plant has supplied to the national power system (through unit No 1) an energy amount of  840 million kWh.

The  Lai Chau hydropower plant project

- Approved by the Prime Minister in Decision No. 822/QD-CP on June 7, 2010

- Project owner: Vietnam Electricity

- Location: Nam Nhun town, Nam Nhun district, Lai Chau province

- Installed Capacity: 1,200 MW (400x3 MW)

- Average annual energy: 4.69 billion kWh

Some major  milestones:

+ Commencement date: Jan 5, 2011

+ The first river blocking: April 24, 2011

+ The second river blocking: October 10, 2014

+ Closing intake gate of diversion tunnel, water storage for the reservoir: June 20, 2015

+ Generation of unit No.1: Dec 2015

+ Generation of unit No.2: June 2016

+ Expected generation of unit No.3: November 2016

+ Expected completion of the whole project: December, 2016

 


  • 20/06/2016 01:45
  • evn.com.vn
  • 1098