The Northern Power Corporation (EVNNPC) held the inauguration and signboarding ceremony for these projects on the afternoon of July 25.

Delegates inaugurate and signboard “110kV Feeder of Vu Thu 220kV Substation” project. Photo: Vu Hue
The 110kV feeder line project from the Vu Thu 220kV Substation, located in Thai Binh Province, is a key infrastructure project. It involves the construction of four new 110kV feeder lines from the 220kV substation, with a total route length of approximately 24.7 kilometers.
The project construction commenced on March 16, 2025, and the first phase was energized on May 28, 2025. This project is designed to utilize the capacity of the Vu Thu 220kV Substation, enhancing transmission capability and electricity supply to the Long Boi, Kien Xuong, Vu Thu, and Thai Binh 110kV substations. Notably, the construction was expedited and completed in just over 1.5 months, surpassing the planned schedule. The early energization holds great significance as it immediately enabled the exploitation of 80MVA from the AT1 transformer at the Vu Thu 220kV Substation. It strengthens power supply capacity for local demand, improves the quality of electricity supply in the region, and promptly meets the electricity needs for economic-social development and the livelihoods of the people.

Comrade Cao Quang Quynh - Member of Standing Committee of Party Committee and Member of Board of Directors of Vietnam Electricity (EVN) - presents commendations to Hung Yen Power Company and Northern Power Project Management Board. Photo: Vu Hue

Comrade Trinh Mai Phuong - Member of Standing Committee of EVN Party Committee, Head of Propaganda Department of Party Committee, and Head of Communications and Corporate Culture Department of EVN - awards Certificate of Merit to Hai Phong Power Company. Photo: Can Minh Thu
Also on the afternoon of July 25, at the DeepC Industrial Zone, the Northern Power Corporation (EVNNPC) held an Inauguration and Signboarding Ceremony for the 110kV transmission line Nam Dinh Vu 1 - Nam Dinh Vu 2 project, located in Hai Phong City. The project is owned by EVNNPC and managed by Hai Phong Power Company.
This is a key project aimed at ensuring a stable power supply for Nam Dinh Vu Industrial Park and DeepC, meeting energy demands and promoting the economic development of Hai Phong City.
The project construction commenced on November 5, 2024, and thanks to the support from the city’s political system and the close direction from EVNNPC’s leadership, Hai Phong Power Company and contractors successfully completed the project ahead of schedule, by March 15, 2025.

Delegates carry out inauguration and signboarding ceremony for 110kV transmission line project Nam Dinh Vu 1 - Nam Dinh Vu 2 in Hai Phong City.
Photo: Can Minh Thu