500 kV Duc Hoa Substation and Connections
Investor:
|
EVN/EVNNPT
|
Project manager:
|
The Southern VietNam Power Projects Management Board
|
Project Consultant:
|
Power Construction JSC No.3
|
Total investment:
|
|
Investment sources:
|
|
Capacity (MVA):
|
900
|
Start:
|
2nd quarter 2016
|
Finish (expected):
|
2017
|