500 kV line connection Nghi Son 2 Thermal Power Plant to National Power grid

09:08, 16/12/2016

Investor:

EVN/EVNNPT

Project manager:

The Central VietNam Power Projects Management Board

Project Consultant:

Power Construction JSC No.3

Total investment:

 

Investment sources:

 

Length(km):

4x50

Start:

2016

Finish (expected):

2018


Share