500kV power line project connecting Nghi Son 2 BOT Thermal Power Plant to the national power system completed

On 27 July 2021, Central Vietnam Power Projects Management Board (CPMB) in coordination with related units energized the entire 500kV power line project connecting Nghi Son 2 BOT Thermal Power Plant to the national power system.

Previously, on 26 March 2021, the phase 1 project had been energized.

The project, which is invested by National Power Transmission Corporation (EVNNPT), is managed and operated by CPMB. The project, which was started on 9 April 2018, crosses Thanh Hoa and Nghe An provinces.

The project consists of 39.6km of two 500kV double-circuit power lines with 219 locations, connecting Nghi Son 2 Thermal Power Plant (Thanh Hoa) with Nho Quan-Ha Tinh 500kV power lines circuit 1 and circuit 2; at the same time, installation of transposition towers on existing 500kV power lines Circuit 1 and Circuit 2.

The 500kV power line project connecting Nghi Son 2 BOT thermal power plant to the national power system has been completed.

These are urgent grid projects approved by the Prime Minister in Decision No. 428/QD-TTg dated 18 March 2016 on the National Power Development Plan (NPDP) for the period 2011-2020 with a vision to 2030 (NPDP VII).

Completion of the project during the complicated development of the COVID-19 epidemic was a great effort of EVNNPT/CPMB and construction units on the construction site, thereby being ready to transmit power from Nghi Son 2 Thermal Power Plant to the national power system.


  • 27/07/2021 03:36
  • evn.com.vn
  • 383