One section of Vinh Tan - Song May - Tan Uyen 500kV transmission line
This is a double circuit 500kV transmission line with a length of 243km, passing through Binh Thuan and Dong Nai provinces, connecting from the 500kV switchyard of Vinh Tan 500kV substation to the branch pylon of Song May - Tan Uyen 500kV transmission line.
After being successfully energized, the transmission line has been detached to correct pending problems; it is scheduled to be put into operation by 27 May 2019.
This project aims at evacuating power generated from Vinh Tan Power Complex in Binh Thuan province to the national power system, meeting the load growth of the Southern region. At the same time, the project will make a bond between other future large power generation projects in the region and the national power system; improving the stability and reliability of the power system.
The project has a total investment cost of more than VND 5,333 billion, invested by the National Power Transmission Corporation (EVNNPT), managed and implemented by SPMB, and will be transferred to Power Transmission Company No. 3 and Power Transmission Company No. 4 for operation upon completion.