Completing the entire 500kV line, circuit 3

At 6:06 a.m. on August 17, the National Power Transmission Corporation (EVNNPT), the Central Power Project Management Board (CPMB), coordinated with relevant units to energize the Vung Ang - Quang Trach 500kV transmission line, thereby marking the completion of the entire cluster of projects of Vung Ang - Quang Trach - Doc Soi - Pleiku 2 500kV transmission line, circuit 3.

Immediately after being energized, each line circuit carries a load of 110MW.

Previously, at 8 p.m on July 31, 2022, this route was technically energized to open the entire 500kV line, circuit 3.

CPMB leaders and on-duty shift at the Quang Trach 500kV substation witnessing the moment of energizing and carrying the Vung Ang - Quang Trach 500kV transmission line

The energization of the Vung Ang - Quang Trach 500kV line project has made a significant contribution to completing the entire 500kV line, circuit 3, project, and at the same time helps to release the full capacity of Vung Ang Thermal Power Plant on the national power system, strengthen the transmission capacity of the 500kV power grid, contributing to ensuring power supply for Ha Tinh, Quang Binh, Quang Tri, Thua Thien Hue, Quang Nam, Quang Ngai, Gia Lai, Kon Tum, Da Nang and surrounding provinces.

The  Vung Ang - Quang Trach 500kV transmission line from the  Vung Ang 500kV Substation (Ha Tinh) to the  Quang Trach 500kV Distribution yard (Quang Binh) is more than 32km long.

The overall project of Vung Ang - Quang Trach - Doc Soi - Pleiku 2 500kV transmission line:

- Investor: National Power Transmission Corporation;

- Project management unit: Central Power Project Management Board;

- Consists of 3 component projects:

+ Quang Trach - Vung Ang 500kV transmission line and 500kV distribution yard of Quang Trach Power Center;

+ Quang Trach - Doc Soi 500kV transmission line;

+  Doc Soi - Pleiku 2 500kV transmission line;

- Total investment: VND11,949 billion;

- Commencement date: December 18, 2018;

- Energization for the route: July 2022

- Overall scale of the 3 projects includes:

+ Building nearly 742 km of new dual-circuit 500kV transmission line passing through 9 provinces/cities

+ Building 08 new 500kV bays at the distribution yard of Quang Trach Power Center;

+ Expanding numbers of 500kV bays at  Vung Ang, Doc Soi and Pleiku 2 500kV substations;

+ Building 03 new optoelectronic repeater stations and 03 operating houses of the power transmission team.


  • 17/08/2022 10:47
  • evn.com.vn
  • 514