Construction investment of EVN achieved many positive results in the first 6 months of the year

In the context of the COVID-19 pandemic, Vietnam Electricity (EVN) and its units still completed and energized 64 projects and started 64 110-500kV power grid projects in the first 6 months of 2021.

The 220kV Lao Bao substation was energized on June 30, 2021. Photo: Huyen Thuong 

Some important projects have been energized such as: My Tho-Duc Hoa 500kV transmission line, Pha Lai 220kV transmission line branching off Hai Duong, energizing AT2 transformer of 220kV Thanh Nghi substation, energizing 220kV Lao Bao substation and energizing the  500kV Doc Soi-Pleiku 2 power line (belonging to the project cluster of 500kV transmission line circuit 3).

For power source projects, EVN and the French Development Agency (AFD) signed a credit agreement for the preferential loan without a government guarantee, worth €74.7 million (equivalent to VND 1,900 billion, accounting for 30.8% of the total project investment capital) for the Ialy extended Hydropower project (HPP); signed contract for package 15 (EPC-QTI) worth about VND 30,236 billion and signed a credit contract to borrow capital for Quang Trach I Thermal Power Plant project.

From now until the end of the year, EVN strives to complete the power generation of the extended Da Nhim hydropower project in August 2021; speeding up the construction progress of expanded Hoa Binh,  expanded Ialy hydropower projects, Quang Trach Power Center Infrastructure project.

At the same time, EVN strives to ensure the plan of energizing power grid works: connecting Hai Duong and Nghi Son 2 BOT thermal power plants; projects for releasing renewable energy for the Quang Ngai - Quy Nhon 220kV transmission line (Quang Ngai - Phu My section), the Nha Trang - Thap Cham 220kV line, the Cam Ranh 220kV substation and the Dong Ha - Lao Bao 220kV transmission line; ensuring power supply for the 500kV West Hanoi - Thuong Tin transmission line, the 500/220kV Nho Quan - Phu Ly - Thuong Tin transmission line...

Along with that, EVN will start construction of key projects such as: Van Phong 500kV substation, Van Phong - Vinh Tan 500kV transmission line, increase the capacity of Pleiku 2 500kV substation, increase the capacity of  Dak Nong 500kV substation, Tuong Duong 220kV substation, Nam Sum - Nong Cong 220kV transmission line...