According to the report of the Power Project Management Board 2 on Quang Trach I TPP, the overall project progress has reached 56.76%. Of which, design work reached 84.22%; procurement reached 60.3%; and construction and installation work reached 11.8%.
Regarding the infrastructure of Quang Trach Power Center, up to now the compensation and site clearance work has been completed and handed over to the contractor for many construction items such as Quang Trach I TPP, coal import port, distribution yard, shared items such as cooling water pipes, coal conveyors, coal port access roads, return water pumping systems, auxiliary areas, return drainage channels, etc.
Bidding packages serving the construction of main items such as the electrical system, building the fence gate of Quang Trach I TPP, leveling the plant site, renovating the house and office of the Project Management Board, constructing a return drainage canal... has been basically completed, meeting the required schedule.
Regarding the volume of infrastructure construction at Quang Trach Power Center, the construction to date has reached about 82%. In particular, some items reached 100% volume such as the construction of drilling piles and prefabricated structures for coal import port and access bridge; concrete construction of port surface; and installing prefabricated prestressed beams of access bridge. In addition, concrete pouring of the bridge surface reached 79.9%; and construction of stone embankments of all types reached 95.5%.
Regarding project quality, construction activities are monitored and carried out in accordance with the quality management process of the contract and current regulations.
It is expected that unit 1 of Quang Trach 1 TPP generate electricity in June 2026, and unit 2 in October 2026. The project commenced in December 2021.