Determined to complete 500kV Circuit 3 Transmission Line Project on schedule as directed by Prime Minister

On May 29, in Hanoi, Chairman of Vietnam Electricity (EVN) Board of Directors Dang Hoang An chaired a meeting to review the progress of pole erection and wire pulling of the 500kV Circuit 3 Transmission Line Project from Quang Trach to Pho Noi. The meeting was held in both direct and online formats.

The meeting was attended by EVN President and CEO Nguyen Anh Tuan, EVN Board Member Nguyen Duc Cuong, leaders of the National Power Transmission Corporation (EVNNPT), Power Corporations, Power Project Management Boards of Northern and Central (under EVNNPT), and leaders of contractors participating in the project.

At the meeting, the Northern and Central Power Project Management Boards reported on the implementation progress of 4 component projects of the circuit 3 transmission line project from Quang Trach to Pho Noi, including Quang Trach - Quynh Luu, Quynh Luu - Thanh Hoa, Nam Dinh 1 Thermal Power Plant (TPP) - Thanh Hoa, and Nam Dinh 1 TPP - Pho Noi.

EVN Chairman Dang Hoang An chairs the meeting

EVN/EVNNPT reviewed and mobilized specialized staff, engineers, and workers from power transmission companies (under EVNNPT), power corporations, Viettel Group, etc. to support contractors in erecting poles and pulling wires, with the highest effort to complete the project on schedule.

At the meeting, leaders of the contractors also reported on the progress of erecting poles and pulling wires of the packages implemented by the units. Most of the contractors shared about the difficulties in mobilizing human resources to erect poles.

Speaking at the meeting, Chairman of the EVN Board of Directors Dang Hoang An said that at the meeting on May 23, the Prime Minister continued to emphasize the importance of the project and directed that the energization must be implemented in June 2024. The time has remained very short (about 32 days), while the remaining workload is very large.

EVN leader requires that units learn from experience and need to make more efforts, increase human resources, and increase construction time to speed up the progress of work items. Especially, under recent unusual weather, it is necessary to arrange a reasonable and effective construction plan, and speed up the progress of erecting poles and pulling wires.

For all locations, when the steel poles arrive at the construction site, there must be workforces to immediately erect the poles. Leaders of construction contractors need to be closer to the construction site to have timely direction for construction forces and closely follow the progress committed to the investor - Chairman of EVN Board of Directors required.

To control progress, contractors participating in the project need to continue to be proactive and closely coordinate at all stages, from supplying steel poles, equipment, and accessories to construction work on site. Above all, it is the sense of responsibility, working together, joining forces with the highest determination to bring the project to the finish line on schedule according to the Prime Minister's direction, for the common benefit of the country, the Chairman of EVN Board of Directors emphasized.

Progress of the 500kV circuit 3 transmission line project from Quang Trach to Pho Noi as of May 29:

- Completed handover of 100% of foundation positions and 489/503 spans.

- Construction work: Completed casting of 1,174/1,177 foundation positions, constructing 3 remained foundation positions; completed erection of 465/1,177 steel poles; erecting 238/1,177 steel poles; completed pulling wires for 13/503 spans.


  • 29/05/2024 12:12
  • evn.com.vn
  • 155