Vinh Hau 110kV substation officially put into operation 2 months ahead of plan.
Hoa Binh - Dong Hai 110kV transmission line project, commenced in September 2019, consists of a total length of 34,385km, 2 circuits, total investment of VND 134 billion. This is one of the key projects of EVNSPC in 2021, contributing to enhancing the power supply capacity, meeting the power supply demand and economic development in Hoa Binh and Dong Hai districts (Bac Lieu province); at the same time contributing to releasing the capacity of Dong Hai 1, Hoa Binh 1 and Hoa Binh 2 wind power plants.
Vinh Hau 110kV substation was commenced in November 2020, with a total investment of VND 113.5 billion (including the Hoa Binh - Bac Lieu 2 110kV transmission line), implemented with ODA loans of German Government (KfW). The station was built in an unmanned model, with the scale of installing 2 transformers (40MVA/unit); in which 1 unit is to be installed in the first stage.
When the Vinh Hau 110kV substation is put into operation, it will meet the rapidly developing load demand of Hoa Binhdistrict; strengthen power links and prevent overload for the 110kV power grid, reduce power loss and improve voltage quality and reliability of power supply for Hoa Binhdistrict, Bac Lieu province.