The working program took place from 30 October to 1 November 2024.
State Inspection Council for Construction Acceptance chairing working session on preparations for flooding of energy line of Ialy Hydropower Plant Expansion Project. Photo: Hien Tran.
According to the report of EVNPMB2, the completed construction items and works serving the flooding of the energy line are the entrance channel, water intake, water tunnel, pressure tower, pressure pipeline, plant (the construction part of the plant and related equipment including disc valve, turbine, leaking water pump system, flood prevention, draining the system and compressed air system, self-consumption power supply), discharge channel, diversion channel of the Ialy Hydropower Plant Expansion Project (construction site in Ya Tang commune, Sa Thay district, Kon Tum province and Ia Mo Nong commune, Ia Kreng commune, Ialy town, Chu Pah district, Gia Lai province). The new energy line and plant are designed to be built on the left side of the existing line, independent of the items of the existing Ialy Hydropower Plant.
Mr. Nguyen Duc Minh, Deputy Director of Power Project Management Board 2 reporting current status of construction items to State Inspection Council
Mr. Nguyen Duc Minh - Deputy Director of Power Project Management Board 2, Director of the Project Management Board, said that the Ialy Hydropower Plant expansion work has been basically completed by the approved design, the construction quality meets the requirements of the design documents, and the acceptance organization of the construction items following the law.
EVN Vice President Pham Hong Phuong speaking at meeting
The State Inspection Council on Construction Acceptance work has agreed that the work meets the conditions for flooding the energy line and generating power for Unit 1.
Previously, the Investor-level Acceptance Council chaired by EVN Vice President Pham Hong Phuong met and accepted the completion of the flooding service for the energy line on 30 October 2024.