Specifically, in the above resolution, the Government has agreed to a pilot policy to allow impacts on natural forests in La Dee, Cha Val, Ta Bhin, and Ta Po communes, Nam Giang district, Quang Nam province to implement temporary works (public service road and material storage yard) serving the construction of the foundations of the Monsoon - Thanh My 500kV power line project (section in the territory of Vietnam).
The Government assigned the People's Committee of Quang Nam province to direct the provincial authorities in coordination with Vietnam Electricity to review the design documents, determine the exact location, construction scale, and duration of temporary works, area and status of forests that need to be impacted to implement temporary works (public service road and material storage yard) to serve the construction of the foundations of the Monsoon - Thanh My 500kV power line project.
The Government assigned Vietnam Electricity to review the design of temporary works, and accurately determine the need to use natural forests to implement temporary works (public service road and material storage yard) for the construction of the project.
After completing the construction of temporary works, the forest must be restored and handed over to localities and forest owners for management according to the provisions of the law on forestry.