The transformer T2 with capacity of 40MVA and 5 outputs of 22kV, 35kV. After being put into operation, the project will contribute to ensuring stable power supply to the key enterprise load in the area. At the same time, creating loop-circuit link in the power supply between 3 stations of Doi Coc 110kV, Luc Nam 110kV and Luc Ngan 110kV; to meet the demand for load development in Luc Nam, Luc Ngan and Son Dong districts under the direction of Bac Giang Provincial People’s Committee.
Particularly, Luc Nam 110 kV transformer station has the scale of 2 transformers x 40 MVA-110/22kV and 12 ouputs of 22kV, 35kV. In which, the transformer T1 with 7 feeders was energized and put into operation by EVNNPC in 2014.