17:30, 15/12/2016
Investor:
EVN/EVNNPT
Project manager:
The Central VietNam Power Projects Management Board
Project Consultant:
Total investment:
Investment sources:
Length (km):
80
Start:
2nd quarter 2016
Finish (expected):
3rd quarter 2017
09:26, 16/12/2016
09:25, 16/12/2016
09:24, 16/12/2016
09:23, 16/12/2016
5th Congress of Vietnam Electricity’s Youth Union: "Aspiration - Courage - Creativity"
Annual Report 2024-2025
Key objectives and targets of EVN for 2026
Electric Power Trading Company: Overcoming difficulties and challenges, basically achieving targets set for 2025
Power grid investment and construction in 2025: EVNSPC surpasses its targets
EVN launches major power projects
EVN simultaneously breaks ground and inaugurates multiple power projects and works in celebration of 14th National Congress of Communist Party of Vietnam
EVN’s Vice President Nguyen Tai Anh inspects construction progress of Quang Trach I Thermal Power Plant
Inauguration of Hoa Binh Hydropower Plant Expansion: Additional 480MW power to the national grid
AFD provides 76-million-EUR loan for Vietnam’s first pumped-storage hydropower plant