95% site of the 500kV line – circuit 3 handed over

According to the Central Power Projects Management Board (CPMB), by the end of August 2020, on the whole Vung Ang - Quang Trach - Doc Soi - Pleiku 2 500kV line - circuit 3 has been handed with over 1,522/1,606 foundation positions,  reaching 95% of the plan.

Construction of 500kV transmission line -circuit 3 through Quang Nam province

Specifically, the whole line has been inventoried at 100% of the plan. The handover of site has reached 95% of the plan. In which, there localities have completed 100% of the plan, including Thua Thien Hue, Kon Tum and Gia Lai provinces. Some localities have gained low rates such as Ha Tinh province with 60/71 locations (reaching 85%); Quang Nam 225/268 positions (reaching 84%); Quang Ngai 187/196 positions (reaching 95%).

The main difficulty in the project's site clearance and compensation work is the forest land conversion procedure. In Quang Nam, there has been a decision made on the conversion of forest use purposes, the locations that have not been handed over are mainly the ones in progress of completing procedures for forest tree recovery. Quang Ngai province is proceeding procedures to submit them to   the Provincial People's Committee for the conversion.

Regarding the construction progress, up to now, 1,443/1,606 positions of the foundation have been excavated (reaching 89.9% of the plan); 1,096/1,606 columns erected (reaching 68.2% of the plan). Due to the COVID-19 pandemic, localities required declaration and social-distancing implementation, which also largely  affected the construction progress.

To complete the project by December 2020, CPMB and localities strive to completely hand over the foundation items and corridor in October 2020. Difficulties and problems in the implementation of rope pulling will continue to be resolved until mid-November 2020.


  • 01/09/2020 03:28
  • evn.com.vn
  • 331