Quang Binh: Handing over the entire site plan for the third circuit of 500 kV transmission line in September 2020

According to Document No. 1475 / UBND-KT dated August 21, 2020, the People's Committee of Quang Binh province requires departments, agencies, local authorities and  relevant organizations to keep on seriously executing the instructions of the provincial People's Committee on removing difficulties and obstacles in compensation and site clearance activities for construction of the project of the third circuit of 500 kV transmission line; at the same time, more attention should be paid to realizing the recommendations of the Party Committee of Vietnam Electricity, the Party Committee of Central Power Project Management Committee (CPMB) on schedule.

A tower site in the project of the third circuit of 500 kV transmission line, the line section going through Quang Binh province

The People's Committee of Quang Binh province has requested Quang Trach district to take measures to force households not to obstruct contractors from constructing the 500 kV distribution switchyard of Quang Trach Power Center and Quang Trach - Vung Ang 500 kV transmission line. As for Quang Trach - Doc Soi 500 kV transmission line, the People's Committee has requested the districts of Quang Trach, Tuyen Hoa and Quang Ninh to urgently complete and approve compensation and site clearance plan for outstanding locations. To maintain communication activities so that households are motivated to receive monetary compensation and hand over the ground of 10 remaining foundation locations (05 positions in Quang Ninh district, 04 in Quang Trach district and 01 in Tuyen Hoa district), completing before August 30, 2020; to urgently complete the construction of the concentrated resettlement area, allocate land for households having houses and architectural structures in the right of way; prepare and approve compensation and site clearance plan, promptly make payment for affected households, and hand over the site plan for the entire right of way before September 30, 2020.

The People's Committees of Bo Trach, Le Thuy districts and Dong Hoi city have requested the Land Fund Development Center, the Land Fund Development Construction and Investment Project Management Board and relevant organizations to concentrate their manpower on fulfilling the compensation and site clearance plan, submitting and approving the part relating to houses, architectural structures and trees in the remaining tower locations, paying for and handing over the ground for the entire right of way before September 20, 2020.

People's Committees of districts of Quang Trach, Tuyen Hoa, Le Thuy, Bo Trach, Quang Ninh, Ba Don town, Dong Hoi city have directed communes, wards and towns to notify the remaining households and entities who have assets, trees in the right of way and have already received compensation and require their support in utilizing and cutting trees before August 25, 2020. After the above deadline, for those fail to utilize and cut trees, construction units will do the tree cutting to do the acceptance of the right of way according to current regulations.

In the implementation process, attention must be paid to information and communication activities; ensuring consistency and equality in accordance with laws. In cases that have been informed for many times, fully and properly complying with regulations but fail to obey, the construction security organization shall ensure security and order to support the site clearance to secure the project construction on schedule.


  • 25/08/2020 05:10
  • evn.com.vn
  • 246