Package 63 in Binh Giang district (Hai Duong province) includes 14 foundation locations (locations: from 275 to 288), including 3 post foundations with 6 anchor intervals (equivalent to nearly 6km of power line), including 2 anchor locations using 2-body posts.
Post-erection of Package No. 63, Nam Dinh I TPP - Pho Noi 500kV transmission line project, has been completed
The leader of Song Hong Power Construction Joint Stock Company 4 added: In parallel with the post-erection process, the Company has calculated a reasonable time to organize the cable-pulling plan, for each completed post-erection anchorage section, the unit shall immediately organize the cable-pulling and up to now the unit has organized the cable-pulling for 2/6 of the anchor sections. After the last post position of the package is completed, the unit shall focus on cable-pulling and is determined to complete this package before June 15, 2024, ahead of schedule.
The completion of the first post-erection package of the Project is of great significance, motivating other units to actively strive with the highest determination to bring the project to completion as scheduled.
Project Nam Dinh I TPP - Pho Noi 500kV Transmission Line :
- Approximately 127km long,
- Passing through the provinces of Nam Dinh, Thai Binh, Hai Duong and Hung Yen.
- There are 334 post foundation positions, with 144 anchorage sections along the line.
- As of noon on May 26, 2024: 331/334 foundation positions have been completed; 210 steel posts have been supplied to the construction site; 192 posts have been completed and are being installed; 2 anchorage sections are being pulled.
|