Member of EVN Board of Directors Nguyen Duc Cuong chairing the meeting
According to Mr. Nguyen Quang Trung, Deputy General Director of EVNHANOI, in the first 6 months of 2023, EVNHANOI commenced a project "Building a 220kV transmission line from Tay Hanoi 500/220kV Substation to Thanh Xuan 220kV Substation” on June 21, 2023. Besides, EVNHANOI has energized 3 works including Building a new underground cable line from Nghia Do 110kV Substation to Thu Le Park 110kV Substation; Expanding Nghia Do E1.9 110kV Substation; Installing horizontal compensating capacitor 40MVAr at 110kV voltage level at Van Dinh E10.2 110kV Substation. The additional equipment capacity is 63MVA and 4.4km of conductors.
According to the plan, in the last 6 months of the year, EVNHANOI shall make every effort to energize six 110kV grid projects, and at the same time commence three projects (one 220kV grid project and two 110kV grid projects).
Regarding the implementation of 220kV power grid projects on the list of key projects, the "New construction of Thanh Xuan 220/110kV Substation project" has been commenced, however, it is facing difficulties and obstacles in ground clearance. The remaining two projects are the "Project to build 220kV transmission line from Tay Hanoi 500/220kV Substation to Thanh Xuan 220kV Substation" and "New construction of Dai Mo 220/110kV substation and its 220kV branch". These projects are expected to begin in the third quarter of this year.
EVN Vice President Pham Hong Phuong speaking at the meeting.
According to EVNHANOI’s representative, each unit under EVNHANOI has established a part-time project management board within the unit to manage construction investment projects. This model has helped the units to increase their initiative in performing assigned tasks, smoothing project management, and ensuring the progress of construction investment.
Mr. Nguyen Anh Tuan - Chairman of EVNHANOI's Board of Directors speaking at the meeting