The project is invested by Northern Power Corporation (EVNNPC) with a total investment of nearly VND 37 billion, in the installation scale of a 63MVA - 115/38.5/23kV transformer and synchronous equipment, 4 22kV outgoing feeders.
With 4 63MVA transformers, the Yen Phong 3 110kV substation will promptly meet the demand of load growth of Yen Phong IZ during period of until 2020.
This station has been put into operation by EVNNPC since 2015, supplying power to the main load of Samsung Display Yen Phong hi-tech complex and a part of residents living in the area.