EVNNPT basically and completely handles failures of 220-500kV power grid caused by Typhoon No. 3

Up to noon on 9 September  2024, the failures on the 220-500kV transmission grid caused by Typhoon No. 3 (YAGI) have been basically and completely handled by the National Power Transmission Corporation (EVNNPT).

EVN Vice President Ngo Son Hai (first from left) listening to leader of Power Transmission Company 1 report on support work to replace damaged equipment at 220kV Distribution Yard of Uong Bi Thermal Power Plant on evening of 8 September 2024

Typhoon No. 3 caused several failures on the 220-500kV power grid, mainly concentrated in the Quang Ninh and Hai Phong areas. Immediately after the Typhoon passed, EVNNPT requested Power Transmission Company 1 to mobilize maximum human resources, working through the night to handle the failures caused by Typhoon No. 3 most quickly.

In addition, with the target of supplying safe, reliable, stable power and being ready to support other units, EVNNPT sent a working team under the direct direction of the Deputy Director of Power Transmission Company 1 to participate in supporting the supply and replacement of damaged equipment at the 220kV distribution yard of Uong Bi Thermal Power Plant to restore the plant's power generation.

EVNNPT leaders inspecting work of handling damage caused by natural disasters and inspecting work of re-energizing Quang Ninh 500kV substation

On the evening of 7 September 2024,  after the Typhoon passed, 8/9 substations were restored to operation, ready to supply power to the load. EVNNPT has directed PTC1 to focus all resources on putting the remaining equipment into operation as soon as possible. Up to now, EVNNPT has basically completed supplying power to the load.