Energizing stage 2 at Project of raising the capacity of Vinh Tan 500kV Substation

On 28 May 2020, at 500kV Vinh Tan substation (Binh Thuan province), the Southern Vietnam Power Projects Management Board (SPMB) coordinated with relevant units in successfully energizing and accepting the AT2 500kV-900MVA transformer.

The project of raising the capacity of the 500kV Vinh Tan substation is invested by the National Power Transmission Corporation (EVNNPT and managed by the SPMB.

The successful energization of AT2 transformer contributes to the release, collection and transmission of the entire capacity of renewable energy plants in ​​Binh Thuan and Ninh Thuan provinces. It also contributes to ensuring stable, continuous and safe power supply, serving socio-economic development and national defense security of Binh Thuan province and neighbouring areas.

Previously, the AT1 500kV-900MVA transformer was energized on 17 April 2020.

The work is affixed with the name board “Work welcome the 3rd National Congress of Power Transmission Corporation's, term 2020 – 2025” by EVNNPT's Standing Committee under Decision No. 386-QĐ/ĐU dated 27 March 2020. It is expected that the name board affixing will be organized on 5 June 2020.


  • 29/05/2020 04:57
  • evn.com.vn
  • 483