Project cluster to release capacity of Van Phong 1 BOT Thermal Power Plant:
- Investor: National Power Transmission Corporation;
- Project management and operation: Central Power Project Management Board;
- Receiving and operating unit: Power Transmission Company 3
- Total investment: VND 3,652 billion.
Van Phong 500kV substation and its connection:
+ Location: Ninh Hoa town, Khanh Hoa province.
+ Commencement: September 2021.
+ Energization: November 28, 2022.
Van Phong – Vinh Tan 500kV transmission line:
+ The project passes through Khanh Hoa province (Ninh Hoa, Dien Khanh, Cam Lam districts and Cam Ranh city) and Ninh Thuan province (Bac Ai, Ninh Phuoc, Ninh Son, Thuan Nam districts).
+ Scale: New construction of a dual-circuit transmission line about 156.78 km long from Van Phong Thermal Power Plant to Point D (G36A) – Connection point of Thuan Nam 500kV substation to Van Phong 500kV Thermal Power Plant – Vinh Tan Thermal Power Plant.
+ Completion: December 26, 2022.
The 500kV line connects Thuan Nam 500kV substation to Van Phong - Vinh Tan 500kV transmission line:
+ The line passes through Thuan Nam district, Binh Thuan province.
+ Scale: About 1.3 km.
+ Completion: December 26, 2022.
|