Successfully energizing and synchronizing power unit No.4 of Trung Son Hydropower Plant with the power grid

On June 20, 2017, power unit No.4 of Trung Son Hydropower Plant located at Trung Son commune, Quan Hoa district, Thanh Hoa province was officially energized and successfully synchronized with the national power grid.

The successful synchronization of Power unit No.4 – the last power unit of Trung Son Hydropower Plant took place only two months after power unit No.3 being energized. Upon putting all the four power units of Trung Son Hydropower Project into operation, the whole plant will contribute an annual average generation output of 1.018 billion kWh to the national power grid, at the same time the plant will help control floods and irrigations for downstream areas of Ma river. In particular, the project will be a driver for the local economic development, hunger eradication and poverty reduction process in Quan Hoa district, Thanh Hoa province.

Trung Son Hydropower Project has been assigned by Vietnam Electricity to Trung Son Hydropower One Member Limited Liability Company under Power Generation Corporation 2 to be the project owner. The plant is composed of four power units with the total installed capacity of 260 MW. This is the first hydropower project being financed by the World Bank in Vietnam. It is targeted that Trung Son Hydropower Project can minimize its social and environmental impacts that may be caused by project related construction and operation activities. Especially living conditions of project affected people will be remarkably improved after the project is completed. The project creates environmental benefits, contributes to reducing Green House Gas emission (GHGs) in comparison with other fossil fueled power plants of similar size.

INFORMATION OF TRUNG SON HYDROPOWER PROJECT

1. Project participants:

- Project development and designing consultant: Power Engineering Consulting No. 4 JSC.

- Project contractors: a Consortium between Samsung C&T and Construction Company No.47; Hydraulic mechanical contractor: Vietnam Machinery Installation Corporation – LILAMA; Electro – mechanical contractor: Hydropower China Corporation.

- Project construction supervision consultant: AECOM New Zealand Limited (New Zealand) and its Sub – Consultant Dong A Investment and Construction Consulting Company

2. Project’s main parameters:

Catchment area (Flv): 14.660 km2

- Reservoir capacity (Wtb): 348.5 million m3

- Reservoir surface area at full supply level: 13.13 km2

- Full supply level: 160 m

- Minimum supply level Mực nước chết (MNC): 150 m

- Flood control storage (Wfl): 150 million m3

- Regular flood control storage: 112 million m3

- Installed capacity (Nlm): 260 MW

- Mean annual electricity (Eo): 1,018.61 million kWh

- Dam crest length: 513 m, dam crest width: 8m

- Dam height: 84,5 m

- A power plant containing four 65 MW Francis turbines (total installed capacity of 260 MW), is designed for a maximum water head of 72.02 m

- A 220 kV transmission line of 65 km long connecting to Vietnam national grid (invested by the National Power Transmission Corporation).

- An access road of 20.4 km long, 6.5 m wide sub-grade and  5.5 m wide pavement with two big bridges (132 m and 264 m long) and five medium bridges (four of 33 m long, one of 72 m long) connecting from the main road system to the Project site.

- Social, environmental and public relation programs have been conducted to mitigate foreseeable and unforeseeable impacts of the Project on around 10,600 Project directly and in directly affected  people (2,327 households), including 7,012 directly affected people (1,516 households) at the Project’s main site, 553 households (2,450 people) have to be resettled.

CONTACT INFORMATION:

Vietnam Electricity

Public Relation Department

Telephone: 04.66946411/66946413  

Address: 11 Cua Bac Str., Truc Bach, Ba Dinh district - Ha Noi; 

Website: www.evn.com.vn, www.tietkiemnangluong.vn

Trung Son Hydropower One Member Limited Liability Company

Tel: 04 37100596, Fax: 04 37100597

Address: 6th and 7th floor, VEAM Building, 689 Lac Long Quan – Phu Thuong – Tay Ho district – Ha Noi.


  • 21/06/2017 11:21
  • evn.com.vn
  • 824