According to updated information, out of 106 wind power plants mentioned above which have applied for COD testing, by 29 October 2021, 42 wind power plants with a total capacity of 2131.3MW have been accepted for commercial operation (details as attached table).
With the spirit of maximum support to wind power plant investors, relevant organizations under EVN have made their best efforts and actively coordinated with wind power plants that have applied for testing and requested COD acceptance.
EVN will keep on updating and informing on the progress of commercial operation (COD) acceptance of wind power projects until the end of 31 October 2021.
CONTACT INFO:
Communication Department - Vietnam Electricity Corporation;
Email: bantt@evn.com.vn
Phone: 024.66946405/66946413; Fax: 024.66946402
Address: No. 11, Cua Bac Street, Truc Bach Ward, Ba Dinh District - Hanoi;
Website: www.evn.com.vn, www.tietkiemnangluong.vn
Fanpage: www.facebook.com/evndienlucvietnam