Updated information on the status of commercial operation date (COD) for wind power plants as of 22 October 2021

As reported by EVN, a total of 106 wind power plants have submitted documents and application forms for registration of grid energization and connection, testing, and commercial operation date (COD).

The total registered capacity for COD testing of these 106 wind power plants is 5655.5MW.

According to updated information, from 1st – 22nd October 2021, a number of wind power plants with specific capacity levels have been recognized for COD as follows:

NAME OF WIND POWER PLANT

COD-RECOGNIZED POWER (MW)

Phuong Mai 1

24.00

Huong Tan

46.20

Tan Linh

46.20

Nhon Hoa 1

50.00

Nhon Hoa 2

50.00

BT1

109.20

Energy Conqueror

49.80

Lien Lap

48.00

Gdex2

25.20

Tan Thuan - stage 1

20.80

Ea Nam

126.70

Hoang Hai

34.10

V1-2 Tra Vinh

48.00

No.7 Soc Trang

16.80

Phong Huy

16.00

Phuoc Minh

23.80

Ia Bang 1

41.60

IaPet-DakDoa 1

67.20

Han Quoc- Tra Vinh

48.00

Tai tam

16.00

PhongLieu

24.00

Hong Phong 1

40.00

Phong Nguyen

16.00

 

Thus, on 22nd October 2021, 28 wind power plants with a total capacity of 1247.4MW out of 106 wind power plants of 5655.5MW registered for COD testing, have been recognized with COD. EVN will continue to update and inform on the progress of COD recognition of wind power projects before 31st October 2021.

CONTACT INFO:

Communication Department - Vietnam Electricity Corporation;

Email: bantt@evn.com.vn

Tel: 024.66946405/66946413;   Fax: 024.66946402

Address: No. 11, Cua Bac Street, Truc Bach Ward, Ba Dinh District - Hanoi;

Website: www.evn.com.vnwww.tietkiemnangluong.vn

Fanpage: www.facebook.com/evndienlucvietnam

Updated%20information%20on%20the%20status%20of%20commercial%20operation%20date%20(COD)%20for%20wind%20power%20plants%20as%20of%2022%20October%202021.docx


  • 22/10/2021 02:24
  • evn.com.vn
  • 1525