The total registered capacity for COD testing of these 106 wind power plants is 5655.5MW.
According to updated information, from 1st – 22nd October 2021, a number of wind power plants with specific capacity levels have been recognized for COD as follows:
NAME OF WIND POWER PLANT
|
COD-RECOGNIZED POWER (MW)
|
Phuong Mai 1
|
24.00
|
Huong Tan
|
46.20
|
Tan Linh
|
46.20
|
Nhon Hoa 1
|
50.00
|
Nhon Hoa 2
|
50.00
|
BT1
|
109.20
|
Energy Conqueror
|
49.80
|
Lien Lap
|
48.00
|
Gdex2
|
25.20
|
Tan Thuan - stage 1
|
20.80
|
Ea Nam
|
126.70
|
Hoang Hai
|
34.10
|
V1-2 Tra Vinh
|
48.00
|
No.7 Soc Trang
|
16.80
|
Phong Huy
|
16.00
|
Phuoc Minh
|
23.80
|
Ia Bang 1
|
41.60
|
IaPet-DakDoa 1
|
67.20
|
Han Quoc- Tra Vinh
|
48.00
|
Tai tam
|
16.00
|
PhongLieu
|
24.00
|
Hong Phong 1
|
40.00
|
Phong Nguyen
|
16.00
|
Thus, on 22nd October 2021, 28 wind power plants with a total capacity of 1247.4MW out of 106 wind power plants of 5655.5MW registered for COD testing, have been recognized with COD. EVN will continue to update and inform on the progress of COD recognition of wind power projects before 31st October 2021.
CONTACT INFO:
Communication Department - Vietnam Electricity Corporation;
Email: bantt@evn.com.vn
Tel: 024.66946405/66946413; Fax: 024.66946402
Address: No. 11, Cua Bac Street, Truc Bach Ward, Ba Dinh District - Hanoi;
Website: www.evn.com.vn, www.tietkiemnangluong.vn
Fanpage: www.facebook.com/evndienlucvietnam