Central Leaders of Vietnam Fatherland Front, leaders of the Government, leaders of the Vietnam General Confederation of Labor, leaders of localities, EVN, and EVNNPT witnessing representatives of investors and contractors committing to emulation
Delegates attending Emulation Launching Ceremony to build the Quang Trach - Pho Noi circuit-3 500kV transmission line
Previously, in Plan No. 21/KH-TLD-EVN dated 26 February 2024 issued by the Vietnam General Confederation of Labor and Vietnam Electricity, the emulation movement on the construction site of the Quang Trach (Quang Binh) - Pho Noi (Hung Yen) circuit-3 500kV transmission line was launched with the theme " Five best", including Fastest progress; Best quality; Safest - Most economical; Most creative; Best care for workers’ lives.
The emulation period is 120 days and nights from 1 March 2024 to 30 June 2024. Specific emulation targets: Construction completion of casting foundation on 30 March 2024; Construction completion of erecting pole on 30 April 2024; Construction completion of pulling conductor by 28 June 2024; Completion of acceptance and energizing by 30 June 2024.
The emulation movement aims to create a vibrant emulation atmosphere so that units can unite and strive to successfully complete their tasks; At the same time, to arouse a sense of responsibility, the will to overcome difficulties and the spirit of creative work, determination to complete the project's energization by the schedule directed by the Prime Minister.
To date, the project has achieved important results. First of all, the project has completed its investment policy in a very short time (about 4 months); basic completion of bidding packages. On the entire transmission line, 1,143/1,177 (97%) pole foundation positions and 230/502 anchorages (about 46%) have been handed over to the land. Of these, 7/9 localities have completed handing over the entire pole foundation position, the remaining 2 localities, Nghe An and Thanh Hoa, are completing the final procedures to hand over the pole foundation position to the construction contractor.
By the end of 26 February 2024, temporary road construction is being implemented on the entire transmission line; 950 pole foundation positions are being dug and cast; 99 pole foundations are cast completely; 1 steel pole is erected completely and 11 steel poles are being erected.
EVNNPT President and CEO Pham Le Phu reporting at emulation launching ceremony
Currently, EVNNPT and contractors have been making maximum efforts, organizing construction with the motto "4 on-site", "3 shifts, 4 crews" construction, "overcoming the sun and winning the rain", "Only move forward" and “working through holidays and Tet” with the highest determination, working together with the investor to complete the project in June 2024.
Deputy Prime Minister Tran Luu Quang and Chairman of EVN Board of Directors Dang Hoang An discussing solutions to remove problems of project
To strive to complete the project by the Prime Minister's direction, EVNNPT leaders petition the Government, ministries, branches, and localities to promptly remove obstacles within related authority and responsibilities, especially resolve the conversion of forest use purposes and site clearance so that the investor can carry out the next work. The investor also petitions that the leaders of the Provincial Party Committee and People's Committee of the provinces where the project passes through should continue to pay attention and direct relevant departments, branches, and localities to take drastic action to hand over the entire remaining foundation position in February 2024 and hand over the entire corridor before 15 March 2024 so that the unit can carry out construction simultaneously.