EVN Vice President Ngo Son Hai giving speech at conference
In his speech at the conference, EVN Vice President Ngo Son Hai acknowledged the achievements that EVNPSC has achieved, especially in repair and maintenance work, early detection of defects, timely handling, ensuring the effective operation of power plants, contributing greatly to the completion of the general plan of Vietnam Electricity.
Delegates attending EVNPSC "Summarizing work in 2024, deploying tasks in 2025" conference
Specifically, EVNPSC completed 82/90 major repair lists, of which many generator units were repaired ahead of schedule: H2-Ialy by 3 days, H3-Ialy by 5 days, H3-Se San 4 by 7 days, and H2-Huoi Quang by 4 days. The company also completed 171/171 regular repair lists, promptly handled arising defects, and promptly fixed and handled generator unit incidents at hydro and thermal power plants.
The technical and economic indicators, the failure rate, and maintenance downtime rate for units and equipment systems at 11 hydropower plants, 1 thermal power plant (total capacity of 9,142MW), and 2 solar power plants (total capacity of 99MWp) all met and were better than the assigned plan. Other areas such as labor safety, digital transformation, training, professional development, and improving skills for management staff were all promoted.
Some photos of the commendation work at the Conference summarizing the work in 2024 and deploying the tasks in 2025 of EVNPSC:
EVN Vice President Ngo Son Hai presenting EVN Party Committee Certificate of Merit to Party members who have excellently completed tasks for 5 consecutive years (2020-2024) of EVNPSC
EVN Vice President Ngo Son Hai presenting EVN Certificate of Merit to "Excellently completed tasks in 2024" collectives
Translator: Thu Hường