220 kV Binh Long-Tay Ninh Transmission Line

17:34, 15/12/2016

Investor:

EVN/EVNNPT

Project manager:

The Central VietNam Power Projects Management Board

Project Consultant:

Power Construction JSC  No.3

Total investment:

 

Investment sources:

 

Length (km):

2x64

Start:

2nd quarter 2016

Finish (expected):

2017


Share