Completing upgrading capacity of Hai Duong 2 220kV substation

The Northern Viet Nam Power Projects Management Board (NPMB) has coordinated with relevant units to organize energizing power and putting AT2 - 220/110/22kV - 250MVA transformer into operation, and complete the work of “Installing the second transformer - Hai Duong 2 220kV substation”, upgrading its total capacity to 2 x 250MVA.

AT2 transformer of Hai Duong 2 220kV substation successfully energized power.

Due to the sharply-increasing demand on power supply of Hai Duong province, the AT1 - 220/110/22kV - 250MVA transformer at Hai Duong 2 220kV substation is always full of load and overloaded. In order to solve this problem, the National Power Transmission Corporation (EVNNPT) decided to invest in the project of “Installing the second transformer - Hai Duong 2 220kV substation.”

This is a grade-1, group C energy work with a total investment of over VND 72 billion, the NPMB shall on behalf of EVNNPT operate and manage the project. The work scale consisting of: Installing AT2 - 220/110/22kV - 250MVA transformer; installing primary, secondary, control, protection equipment, etc., of total feeders 220kV, 110kV of AT2 transformer; installing spraying system for AT2 transformer and additionally equip automatic fire prevention system.

Putting the second 220/110/22kV-250MVA transformer at Hai Duong 2 220kV substation into operation will ensure safe and stable power supply, contributing to the economic development and energy security of Hai Duong province, the Northern coastal area and improve power supply reliability as well as capacity of the national power transmission system.