Based on reports from investors, EVN updates the progress of construction investment and wind power plant projects put into commercial operation by 22 July 2021 as follows:
- 13 wind power plants with a total capacity of 611.33MW were put into commercial operation.
- 106 wind power plants with a total capacity of 5,621.50 MW are expected to be put into commercial operation before 31 October 2021. However, by 22 July 2021, only 61 wind power plants with a total capacity of 3,487.8MW had sent official dispatches to register their program of energizing and connecting to the grid and testing in accordance with regulations before 90 days.
- 25 wind power plants with a total capacity of 1,912.05MW will not be able to be operated commercially before 31 October 2021.
EVN will continue to update and provide information on the progress of wind power projects put into commercial operation (COD) before 31 October 2021.
CONTACT INFO:
Communication Department - Vietnam Electricity Corporation;
Address: No. 11, Cua BacStreet, Truc Bach Ward, Ba Dinh District - Hanoi;
Email: bantt@evn.com.vn
Website: www.evn.com.vn, www.tietkiemnangluong.vn
Fanpage: www.facebook.com/evndienlucvietnam