This is a project to welcome Thua Thien Hue Province to become a centrally-run city and a project to celebrate the 70th anniversary of the Traditional Day of the Vietnam Electricity Industry (December 21, 1954 - December 21, 2024), the 50th anniversary of the establishment of the Central Power Corporation (October 7, 1975 - October 7, 2025), and to welcome the 15th Congress of the Party Committee of the Central Power Corporation for the 2025-2030 term.
Phong Dien Industrial Park 110kV Substation and Connection Project successfully energized on December 1, 2024
The Phong Dien Industrial Park 110kV Substation and Connection Project was commenced in May 2024, with a total investment of VND 79.3 billion, of which commercial loan capital is VND 49.8 billion, EVNCPC's counterpart capital is VND 29.5 billion. The substation is designed with a scale of 2 transformers with a capacity of 40MVA, phase 1 with a 40MVA transformer; and built a new 110kV transmission line with a length of nearly 0.3km.
EVNCPC’s General Director Ngo Tan Cu: project put into operation 6 months ahead of schedule
With the great efforts and determination of EVNCPC leaders, the Central Power Grid Project Management Board, Thua Thien Hue Power Company and construction forces, leaders at all levels, especially with the support of the locality, the project has now been successfully completed and energized, 6 months ahead of schedule.
The project's early operation is of utmost importance, ensuring timely power supply according to the load development situation, reducing power loss, improving power quality and reliability of power supply in Phong Dien district, Viglacera Industrial Park and neighbouring areas, contributing to the socio-economic development goals of the locality.