Be jointly determined to bring Ialy Hydropower Plant Extension Project to its destination on time

That is one of the instructions of Vice President of Vietnam Electricity (EVN) Pham Hong Phuong when holding an inspection and periodical meeting at the construction site of the Ialy Hydropower Plant Extension Project, on July 10, at Gia Lai province.

Reporting at the meeting, Mr. Nguyen Duc Minh - Deputy Director of Power Project Management Board No. 2 said that in the second quarter of 2024, many items were completed ahead of schedule such as water tunnels, diversion channels, reinforced concrete for the bottom of the discharge canal, dismantling the water intake cofferdam, excavating and reinforcing the canal leading to the water intake, and so on. In which, the dismantling of the cofferdam was completed on June 7, 2024, completing the construction of the diversion canal (an important critical path of the Project), basically completing excavation and reinforcing the channel to the water intake, and basically installing equipment items in all rooms.

EVN Vice President Pham Hong Phuong chairing the meeting

EVN Vice President Pham Hong Phuong (leading, on the left of photo) inspecting project’s construction site

It was determined by the contractors that the third quarter of 2024 will be the time to accelerate, to ensure the generation of 2 power units by the end of 2024 and bring the project to its scheduled destination. Therefore, contractors will be highly determined, concentrate their human resources, make the best efforts, and commit to completing the project following the required schedule.

The contractors need to increase their labor forces, working in 3 shifts, 4 crews as the volume of machine installation work is very large and speeds up equipment handover. Ialy Hydropower Company, EVN Repair Service Center, and production preparation force continue to coordinate closely and provide good support for construction on the construction site, and so on.